Short answer: crane hand signals let one trained signaller (banksman) direct the operator when the operator cannot see the load. The essential signals are hoist, lower, stop, emergency stop, swing, boom up, boom down, extend, and retract. Only one person gives signals, they must be in the operator's clear view, and anyone may give the emergency stop. Your site's lifting plan sets which signal system is used, so confirm it at the pre-lift briefing.
| Signal | How it is usually given | What the operator does |
|---|---|---|
| Hoist (raise load) | Forearm vertical, index finger pointing up, small circles | Raises the hook slowly |
| Lower | Arm extended down, index finger pointing down, small circles | Lowers the hook slowly |
| Stop | Arm extended, palm down, held still or moved side to side | Stops the motion |
| Emergency stop | Both arms extended, palms down, moved quickly side to side | Stops everything immediately |
| Swing | Arm extended, pointing in the direction of swing | Slews the boom that way |
| Raise boom | Arm extended, fist closed, thumb pointing up | Raises the boom angle |
| Lower boom | Arm extended, fist closed, thumb pointing down | Lowers the boom angle |
| Extend boom | Both fists in front, thumbs pointing outward | Telescopes the boom out |
| Retract boom | Both fists in front, thumbs pointing toward each other | Telescopes the boom in |
| Move slowly | Give the signal with one hand, other palm held over it | Repeats the motion at slow speed |
Rules That Make Signals Work
- ✓One signaller only. Two people giving signals is how loads get dropped; the exception is the emergency stop, which anyone may give.
- ✓Stay in the operator's sight, wear high-visibility clothing, and stand clear of the load path.
- ✓Agree the signals before the lift, at the pre-lift briefing, and use only those.
- ✓If the operator loses sight of the signaller or doesn't understand a signal, the operator stops.
- ✓For blind lifts or long distances, use radios with a dedicated channel and a clear call sign.
Which Standard Applies?
International sites in Oman often follow the signals in BS 7121, ASME B30.5, or ISO 16715, and some plants publish their own. The differences are small, but they are differences. Ask the site's lifting supervisor which system the lift plan uses, and brief the crane operator and banksman together before the first lift.