Most crane delays come from missing information rather than from the crane itself: a load heavier than expected, a set-up position that turns out to be soft ground, or a site gate that will not let the crane in without paperwork. A few details shared at booking avoid all three.
The Five Things Your Crane Supplier Needs
| Detail | Why it matters |
|---|---|
| Heaviest load and its dimensions | Sets the minimum crane capacity, including rigging weight |
| Radius: distance from crane to load's final position | Crane capacity falls sharply as radius increases |
| Lift height | Determines the boom length required |
| Ground where the crane will set up | Outriggers put high loads into the ground; soft or backfilled ground needs mats |
| Site access and entry rules | Gate width, overhead lines, and gate-pass paperwork at ports and industrial estates |
Measure the radius from where the crane can really stand, with its outriggers out, not from where you would like it to stand. Parked cars, trenches, stacked materials, and overhead lines often push the crane a few metres further away, and those few metres can change the crane you need. If you are unsure whether the job needs a 25 ton or a 50 ton crane, send the three numbers (weight, radius, height) and let the supplier check them against the load chart.
Preparing the Site
- ✓Clear and level the crane set-up area, and keep it away from recent excavations
- ✓Identify overhead power lines and underground services near the set-up position
- ✓Agree an exclusion zone under the load path and brief everyone on site
- ✓Have the load ready, with lifting points identified, before the crane arrives
- ✓Keep the access route clear: the crane needs room to drive in, turn, and extend its outriggers fully
Lifting Gear and the Lift Team
The crane is only one part of the lift. Agree before the day who supplies the slings, shackles, and any spreader beam, and check they are rated for the load and carry valid inspection tags. Agree who will sling the load and who will signal the operator, and check whether your site requires them to be certified. If the load has no marked lifting points, ask the manufacturer or supplier how it should be slung before the crane is booked, not when it is on the hook.
On the Day
- ✓Confirm the load has arrived, and the gate pass is issued, before the crane leaves the yard
- ✓Hold a short briefing: the load weight, the lift path, the landing point, and who gives the signals
- ✓Keep everyone out from under the load and clear of the crane's slewing area
- ✓Stop and reassess if the wind picks up, the ground moves, or the load behaves unexpectedly
Working Inside Ports and Industrial Estates
Sites at Sohar Port and Freezone, the industrial estates, and other controlled facilities usually require machine documents, inspection certificates, and operator IDs before entry. Send the site's requirements when you book so the paperwork is ready and the crane is not held at the gate.
Weather and Heat
Wind limits safe lifting, especially for large, light loads like panels. In summer, early starts reduce heat stress for the crew, and from June to August outdoor work stops from 12:30 pm to 3:30 pm under the Ministry of Labour's midday break, so plan lifts for the morning. In Salalah, the June–September khareef brings mist and wet ground, so build in allowance when planning lifts there.